Running a humanoid robot POC in a company: phases, KPIs and safety

A proof of concept (POC) with a humanoid robot is not a demo. A demo shows that the robot moves. A POC answers a measurable business question, for example: "can a G1 pick these components from this shelf with an acceptable success rate, safely, under these conditions?". This guide describes how we structure a humanoid POC in a company: discovery, KPIs, safety, the lab phase, the pilot and the go/no-go report.

Why many robotics POCs never lead to a decision

POCs that end up in a drawer almost always share the same problems:

  • A vague goal ("let's see what it can do") instead of a precise question.
  • KPIs defined after the fact, shaped to fit the results instead of measuring them.
  • Safety tackled late, when the robot is already on the shop floor.
  • Jumping straight to the shop floor without a controlled lab phase.
  • No exit criteria: the project never ends, or ends without a clear recommendation.

The phases below are designed to avoid each of these mistakes.

Phase 1: discovery

Discovery turns an idea into a testable question. It involves the people who know the process (production, logistics, HSE, IT) and produces a few clear documents:

  • Task description: the sequence of actions, the objects involved with their weight and size, the workstations, and the variability.
  • Environmental constraints: floors, walkways, lighting, Wi-Fi, and people present.
  • Feasibility against specs: for example, the arm payload Unitree states is about 2–3 kg for the G1 and about 7 kg rated for the H2. If the task needs more, you find out here, not after the purchase. See the G1, H2 and R1 comparison.
  • Choice of platform and configuration: a POC that involves development needs an EDU version, because only EDU versions support third-party development.
  • The POC question and KPIs, written down and agreed before work starts.

"A humanoid is not the right technology" is a possible and legitimate outcome of discovery. If so, it is better to know straight away: see humanoids vs traditional robotics.

Defining the KPIs

KPIs must be measurable, tied to the POC question and fixed before testing. The ones we use most often:

KPIWhat it measuresHow it is captured
Task success rateShare of attempts completed correctlyTest protocol with N repetitions and written success criteria
Cycle timeAverage task duration and its variabilityTimestamped logs from the robot software
Human interventionsHow often an operator has to step in, per hour or per cycleIntervention log with causes
AvailabilityOperating time compared with planned timeStatus logs, stoppages and charging
Actual runtimeReal battery life on the taskBattery telemetry
Safety eventsStops, falls, near missesHSE register and logs

Each KPI gets a success threshold agreed with the client. Without thresholds, the final report cannot say go or no-go.

Safety from day one

A humanoid is a mobile, dynamically stable machine with significant mass: about 35 kg for the G1 and about 70 kg for the H2. Safety has to be designed into the POC from the start, not added at the end. The basics:

  • A risk assessment of the specific application, using the ISO 12100 method and involving the company's health and safety lead.
  • A segregated test area with controlled access and adequate distances.
  • A support system (harness or gantry) during development and the first locomotion tests.
  • Stop procedures documented and tested before any custom code runs.
  • Training for everyone who works near the robot.

On the regulatory side: the 2025 revision of ISO 10218 covers industrial robots and applications, including the collaborative content that used to sit in ISO/TS 15066. For dynamically stable robots such as humanoids, ISO 25785-1 is under development. In Europe, the Machinery Regulation (EU) 2023/1230 applies from 20 January 2027. A POC in a segregated area is a very different context from production use, and the report must say so clearly.

Phase 2: the lab

In the lab, the task is reduced to its simplest form and the software stack is built. Typical activities:

  1. Commissioning: firmware, network, access to the official SDK (unitree_sdk2) and, where needed, ROS 2 (unitree_ros2). Details are in the G1 programming guide.
  2. Simulation: reproduce the task in simulation so you can iterate without risk. Unitree publishes official environments such as unitree_mujoco and unitree_sim_isaaclab.
  3. Collecting demonstration data, if the task suits imitation learning: teleoperation with xr_teleoperate and training with unitree_lerobot.
  4. Repeated trials following the KPI protocol, on a bench that reproduces shop-floor conditions.

The lab phase ends with a first set of measurements. If the KPIs are far from the thresholds, this is the time to stop or narrow the scope, before spending time on the shop floor.

Phase 3: on-site pilot

The pilot takes the robot into the real environment, still in a fenced-off area and with a narrow scope. In this phase you:

  • check the impact of real conditions: light, network, floor, and object variability;
  • measure the KPIs with the same protocol as in the lab, so the data is comparable;
  • collect feedback from operators and managers;
  • note the operating costs that come up: setup time, charging, supervision.

In our approach, the whole process from discovery to report typically takes 8–14 weeks. The actual duration depends on how complex the task is and on the availability of space and people.

Phase 4: the go/no-go report

The final report is the real output of the POC. It should let decision-makers choose without having followed every test. A structure that works:

  1. The POC question and the agreed scope.
  2. KPI results against the thresholds, with the raw data attached.
  3. What worked and what did not, with the causes.
  4. Residual risks and the safety measures needed for any next step.
  5. Recommendation: go (with a roadmap), conditional go (with prerequisites) or no-go (with alternatives, such as a cobot or an AMR).

A well-documented no-go is a valuable result. It avoids a bad investment and makes clear what would have to change, in the technology or in the process, to try again.

FAQ

Which robot should I use for a humanoid POC?

For most exploratory POCs, the G1 EDU is the most practical starting point: it is portable and has the widest official software ecosystem. The H2 makes sense when you need human height or heavier loads. See the G1 operational guide and H2 in Italy.

Do I need an in-house software team?

It helps, but it is not essential. You do need at least one process owner and one safety contact. The SDK, ROS 2 and simulation work can be handed to a technical partner.

Can the POC be funded?

It depends on the project and on the schemes open at the time. It is worth checking before you sign: see financing a robot in Italy.

What happens after a go?

You plan the next phase based on the roadmap in the report: a wider scope, a conformity assessment for the intended use, training and a support plan.

Start a discovery

CALIGO supports companies and labs through every phase of a POC on Unitree platforms: discovery, SDK and ROS 2 development, the lab, the pilot and the report. You can find the service details under Unitree support and development. If you have a task in mind, tell us about it and we will start from the right question.